September 29th, 2008
We still have a short section on Pine loop that needs to be done and also two dead end roads and firehydrant installs. We will need to shut the water of on October 6th to do so, if you have storage tanks please make sure you fill them. We will be putting posts on the website with further information regarding this matter as the project begins.
September 29th, 2008
The new line from the intersection of Forest Meadow Road and Arapahoe to the intersection of Forest Meadow Road and Grand View is complete. Starting on Monday Sept. 29th crews will begin to flush the line to get rid of all contaminants. Once the flushing is complete we will then pull a bacteriologic sample to make sure the water is safe.
September 23rd, 2008
Forest Meadow Road from the intersection of Arapahoe Dr. to the intersection of Forest Meadows and Alexander is off for 24 hrs. due to repair.
September 17th, 2008
The Arapahoe line has reached completion. All of the homes along the line have water. All meters are turned off while we flush the line, please check to see if your meter is turned on. Thank you.
September 3rd, 2008
All of Forest Meadows will be shut down on Thursday night Sept. 4th to be able to make certain conections to continue on with the pipeline. The crew will be reaching the intersection of Arapahoe and Forest Meadow Road Friday morning. The water will need to be shut down in order to finish the pipeline to the intersection of Forest Meadow Road and Grand View Lane. We will however be trying to turn certain sections on in Forest Meadows, but are uncertain at this time what these areas will be. The best way to tell if you have water is just to try it until we finish the pipeline at this time. Thank you for being patient and curtious to all employees regarding this matter.