September 27th, 2006
Crews are within 200 ft from the intersection of Navajo Rd. and Running Deer Circle they will complete the Navajo line and then begin up Running Deer Circle. There is no through traffic on Navajo until crews go up Running Deer.
September 27th, 2006
Work will begin on these two roads 9/28/2006 and should not take very long to complete. Crews will start at the intersection of Tollgate Canyon Rd. and go down The road to Salt Box Circle.
September 20th, 2006
We have got all water restored to Uintah View Rd. and Alexander Canyon. All the pipe line is laid, but there is still minor things to do such as haul off dirt piles and clean up. Please be polite to all crews working on the water project. Thank You PMMW Manager
September 20th, 2006
Navajo Rd. has now been turned on down to the intersection of Navajo Rd. and Yellow Moon. This completes Navajo down to Yellow Moon including Deer Loop, all water has been flushed and if you have a new meter you may turn your water on. If you do not have a new meter the meter crew will be following doing meters in order. Please remember all construction is not complete including hauling off dirt piles, putting gravel in meter pits to stand them up straight ect. Our main objective is getting the water restored ASAP and all other miner stuff at a later date. Please be polite to all employees working on the water projects. Thank You PMMWC Manager.