Tue 22 Aug 2006

PROGRESS ON UINTAH VIEW

Progress on Uintah View is a little behind schedule due to rock and ledge.  Crews were unable to lay pipe for about 4 days due to this rock, we had to jackhammer in order to continue.  The pipe is now down around the sharp corner about half way down and will continue as planned.