Our progress on Navajo Rd. is on schedule as planned, the crews are on there way up Deer Loop this week (8/22/06) and should have it completed by the end of this week (8/25/2006).  Once Deer Loop is completed the crew will head down Navajo and then up Yellow Moon when they reach that intersection, after Yellow Moon they will continue down Navajo and up Running Deer Circle.  We are turning water on as we go so if you are on the upper part of Navajo Rd. it is possible you have water.  Water is also on in the Navajo Drive area.