Archive for August 30th, 2006

UPDATE ON UINTAH VIEW

August 30th, 2006

Crews on Uintah View have got all meters tied back in and water will be restored to those meters by 8/31/2006.  The rest of the pipe line we are hoping to have done by the second week of September,  as long as the digging goes as planned.

UPDATE ON NAVAJO RD.

August 30th, 2006

The crews on Navajo Rd. have completed Deer Loop and are now down to the intersection of Navajo and Yellow Moon.  Digging has gone a little slower due to hard sand stone, but we are still making progress.  Water will be restored down to and up Deer Loop possibly by the 8th of Sept. and we are hoping to have all of Navajo Rd. and Running Deer Circle done by the end of Sept.  Excluding Navajo Drive, if crews are ahead we will go down Navajo Drive and try to complete it this year.

 